Phase 1 Projects Will C. Wood Stadium Vacaville High Parking Lot/Tennis Court Project Vacaville High New Classroom Building Project Willis Jepson Modernization Project Elm Campus ADA Improvements Project Sierra Vista Re-Open Project, Increment 1 Sierra Vista Re-Open Project, Increment 2 Sierra Vista Re-Open Project, Increment 3 Orchard Paving Improvement Project Technology
Future Phases
COC Overview Committee Meetings & Members
California Environmental Quality Act (CEQA)
Contractor Information & Bidding

Will C. Wood Stadium

Will C. Wood Stadium Project Is Underway!!

The design and California Environmental Quality Act (CEQA) process has begun. The CEQA process is necessary to identify any possible environmental impacts and actions necessary to mitigate those impacts. The CEQA analysis is conducted in conjunction with the design process of the project. 

Project Schedule

Design Phase                                August 2015 to August 2016


DSA / Agency Review Phase         August 2016 to December 2016


Bid / Award Phase                        January 2017 to April 2017


Construction Phase                      April 2017 to December 2017 

Comments on Will C. Wood Stadium Projects

Do you have an comments on the Will C. Wood Stadium project? Please send your comments through this email:  wcw-stadium@vacavilleusd.org

Your emails will be sent directly to the Director of Facilities, Daniel Banowetz.