Phase 1 Projects Will C. Wood Stadium Vacaville High Parking Lot/Tennis Court Project Vacaville High New Classroom Building Project Willis Jepson Modernization Project Elm Campus ADA Improvements Project Sierra Vista Re-Open Project, Increment 1 Sierra Vista Re-Open Project, Increment 2 Sierra Vista Re-Open Project, Increment 3 Orchard Paving Improvement Project Technology
Future Phases
COC Overview Committee Meetings & Members
California Environmental Quality Act (CEQA)
Contractor Information & Bidding

Vacaville High New Classroom Building Project

Vacaville High New Classroom Building Project

The new classroom building project is int eh design stage. Over a number of increments we will construct two separate 15 classroom buildings over a number of increments. Currently out to bid is the relocation of the softball field and pad for building #1. 

 

We will be constructing building #1 after moving the softball field back and creating the building foundations and pad. Upon completion of building #1 we will empty 15 portables, moving them into the new building. The portables will be moved off site and the construction of building #2 will begin. 

 

Project Schedule

Feasibility Study                           June 2015 to September 2015


Architect Selection                       September 2015 to November 2015


Design Phase                               November 2015 to October 2016


DSA / Agency Review Phase      October 2016 to February 2017


Bid / Award Phase                        February 2017 to April 2017


Construction Phase                      April 2017 to August 2018

 

The buildings are scheduled to be open for classes in the Fall 2018