Phase 1 Projects Will C. Wood Stadium Vacaville High Parking Lot/Tennis Court Project Vacaville High New Classroom Building Project Willis Jepson Modernization Project Elm Campus ADA Improvements Project Sierra Vista Re-Open Project, Increment 1 Sierra Vista Re-Open Project, Increment 2 Sierra Vista Re-Open Project, Increment 3 Orchard Paving Improvement Project Technology
Future Phases
COC Overview Committee Meetings & Members
California Environmental Quality Act (CEQA)
Contractor Information & Bidding

Willis Jepson Modernization Project

Willis Jepson Modernization Project

This project is in the planning stages. The drawings have been submitted to the Division of the State Architect (DSA) awaiting approval.  

 

Project Schedule

Design Phase                                September 2015 to June 2016


DSA / Agency Review Phase       May 2016 to August 2016


Bid / Award Phase                         August 2016 to October 2016


Construction Phase                      October to August 2017