Phase 1 Projects Will C. Wood Stadium Vacaville High Parking Lot/Tennis Court Project Vacaville High New Classroom Building Project Willis Jepson Modernization Project Elm Campus ADA Improvements Project Sierra Vista Re-Open Project, Increment 1 Sierra Vista Re-Open Project, Increment 2 Sierra Vista Re-Open Project, Increment 3 Orchard Paving Improvement Project Technology
Future Phases
COC Overview Committee Meetings & Members
California Environmental Quality Act (CEQA)
Contractor Information & Bidding

Elm Campus ADA Improvements Project

Elm Campus ADA Improvements Project

This project is currently underway.

Project Schedule

Design Phase                               September 2015 to December 2015


Agency Review Phase                  December 2015 to April 2016


Bid / Award Phase                        April 2016 to May 2016


Construction Phase                      May 2016 to August 2016