Phase 1 Projects Will C. Wood Stadium Vacaville High Parking Lot/Tennis Court Project Vacaville High New Classroom Building Project Willis Jepson Modernization Project Elm Campus ADA Improvements Project Sierra Vista Re-Open Project, Increment 1 Sierra Vista Re-Open Project, Increment 2 Sierra Vista Re-Open Project, Increment 3 Orchard Paving Improvement Project Technology
Future Phases
COC Overview Committee Meetings & Members
California Environmental Quality Act (CEQA)
Contractor Information & Bidding

Sierra Vista Re-Open Project, Increment 2

Sierra Vista Re-Open Project, Increment 2

This increment will add a new multi-purpose room with a kitchen and adding science classrooms to the campus.

 

Project Schedule

Design Phase                               January 2016 to December 2016


DSA / Agency Review Phase       September 2016 to February 2017


Bid / Award Phase                        February 2017 to April 2017


Construction Phase                      April 2017 to August July 2018